Ontario house building costs across generations.

What the same house might cost and how a larger home changes the budget.

Draft 2 for Peter Jordon’s review · Information current to October 8, 2026Branded edition: October 10, 2026Prepared for Peter Jordon, CPA, CA, AACI, P.App. | BrokerJordon Real Estate Advisory Services

Analytical summary of the model budget for the same 2,000-square-foot house: $107,000 in 1981, $206,000 in 2000, $401,000 in 2020, $772,000 in 2025 and $765,000 in H1 2026. Early years are proxy backcasts; budgets exclude land and recoverable GST/HST.

Illustrative same-house project budgets in nominal Canadian dollars. Original chart from the report’s model and cited source data. Land and recoverable GST/HST are excluded; 1981 and 2000 are lower-confidence proxy backcasts. Full components, assumptions and sensitivity cases appear in the report.

Executive summary.

Why does an ordinary house cost so much more to build than it did a generation ago? Part of the answer is that we often build a larger house. But even when the size stays the same, the construction bill, municipal charges and cost of carrying the project have changed substantially.

This paper follows a modest 2,000-square-foot detached house through 1981, 2000, 2020, 2025 and the first half of 2026. The proposed budget rises from about $107,000 in 1981 to $765,000 in H1 2026, excluding land and net of recoverable GST/HST. Those are illustrative estimates assembled from published evidence and stated assumptions. The early years are less certain than the recent ones.

Key takeaways.

  • The same house costs more even after allowing for inflation. The model puts the 2,000-square-foot budget at about $401,000 in 2020 and $765,000 in H1 2026, or $200 and $383 per above-grade square foot. Hard costs account for roughly $267,000 of that $365,000 increase; government fees account for another $65,000.
  • Larger homes add a separate expense. Toronto CMA detached homes built in 1981–1990 had a median above-grade area of 2,240 square feet in the 2018 property data, compared with 2,890 for the 2016–2017 cohort. Applying the larger size to H1 2026 prices produces a proposed budget of about $987,000, or $342 per square foot. The lower unit cost comes from spreading fixed costs across more space.
  • There is no single culprit across every period. Concrete masonry outpaced the selected material indexes over 1981–H1 2026. High borrowing rates were a much bigger burden relative to the budget in 1981. More recently, installed construction prices and municipal charges have mattered much more than the price of lumber alone.

Sources: [1] [2] [3] [4] [7] [10] [11] [12] [18] [19] [22] [24]

For an owner, lender or developer, the useful question is whether the expected selling price can cover this complete budget, the lot and a reasonable return. A higher cost to build does not guarantee a higher market value.

Draft 2 for review by Peter Jordon, CPA, CA, AACI, P.App. | Broker. Information current to October 8, 2026; H1 means January–June, not a full-year forecast. Canadian dollars throughout. Research and illustrative analysis only; not an appraisal, quotation or cost certification. Peter has not been represented as independently verifying the research.

The house we are comparing.

To make the comparison useful, imagine the same straightforward house on the same kind of ready-to-build lot. Keep the floor plan and finish level steady. Then ask what changes in the bill. We can later let the house grow and see how much of the extra cost comes from buying more space.

Item Benchmark assumption
House Two-storey detached wood-frame house; 2,000 sq. ft. above grade; three bedrooms and 2½ bathrooms.
Basement and form Simple rectangular footprint and gable roof; unfinished 1,000 sq. ft. basement; no garage. Basement cost is included, but its area is excluded from the $/sq. ft. denominator.
Quality and site Modest production-style quality on a flat, uncontaminated, serviced lot with normal access; no demolition, unusual soils or elaborate landscaping.
Location and permissions One net new ownership dwelling in former Scarborough, within today’s City of Toronto; already approved lot, with no rezoning, severance, DC credit or exemption.
Economic perspective A GST/HST-registered developer building for a taxable sale, eligible to recover input GST/HST.

The benchmark is an analytical specification, not an approved plan or an actual property.

The totals cover the building, modest site work, construction contingency, specified soft costs, government charges and one year of construction financing. They exclude land, land transfer tax, selling costs and the developer’s return. Off-site servicing, subdivision and parkland obligations are assumed to have been settled in creating the serviced lot; their economic cost belongs outside this building budget, not at zero in the wider development process.

Why this matters now.

The debate over development charges is making the distinction between construction cost and the full project budget especially relevant. A September 28, 2026 federal–Ontario announcement for Barrie linked proposed infrastructure funding with a commitment to reduce residential development charges. Toronto has also adopted a conditional reduction programme. Both developments raise the same practical question: how much does a change in one line of the budget help the project as a whole? [13] [14] [15]

The comparison dates are reference points, not demographic labels. Starting in 1981 gives the selected input series a common history. It does not mean every component of a 1981 house can be reconstructed with today’s precision. Nor does holding the description steady mean an identical design would satisfy every generation’s building code.

A proposed budget for each period.

Start with the dollars. The table below answers what it might cost to build our reference house under one consistent set of assumptions. Read the figures as rounded planning examples, especially in 1981 and 2000. They are not historical invoices or estimates for a specific site.

Period Comparison
1981
Hard costs $87.2
Soft costs $7.6
Financing $8.9
Govt fees $3.3
Total $106.9
2000
Hard costs $177.1
Soft costs $15.3
Financing $8.5
Govt fees $5.4
Total $206.4
2020
Hard costs $283.5
Soft costs $24.5
Financing $11.3
Govt fees $81.4
Total $400.8
2025
Hard costs $549.8
Soft costs $47.6
Financing $28.6
Govt fees $146.2
Total $772.2
H1 2026
Hard costs $550.7
Soft costs $47.7
Financing $20.5
Govt fees $146.5
Total $765.4

Table 1. Proposed cost for the same 2,000 sq. ft. house, in nominal $000. Totals calculated before rounding. Land and recoverable GST/HST excluded. 1981/2000 use proxy backcasts; the 1981 levy is an assumed $2,500. Government fees include City DC, education DC and a permit/admin allowance. [1] [2] [7] [10] [11] [12] [18] [22] [24]

The modern construction anchor is Altus Group’s 2025 GTA range of $200–$275 per above-grade square foot for a single-family house with an unfinished basement. Its $237.50 midpoint gives $475,000 for 2,000 square feet before the excluded project items. Updating that amount with Toronto’s detached-house construction index gives about $476,800 in H1 2026. The guide is a broad benchmark; a small infill contract can price differently. [7] [18]

We then add 5% for modest site work, a 10% construction contingency on building plus site work, 10% of building cost for soft costs, and the separate financing and fee assumptions. In H1 2026, this turns roughly $477,000 of building work into a roughly $765,000 pre-land project budget.

The comparison at a glance.

Supplementary infographic of the illustrative 2,000-square-foot house budget: $107,000 in 1981, $206,000 in 2000, $401,000 in 2020, $772,000 in 2025 and $765,000 in H1 2026. A separate larger-house scenario reaches $987,000 for 2,890 square feet in H1 2026. Full figures, scope and qualifications are repeated in the report tables and text.

Supplementary summary graphic. It repeats the report’s model results and size scenario; all figures and qualifications remain in the report’s tables and analysis. Early-period totals are proxy backcasts, and all totals exclude land and recoverable GST/HST. Original chart using the sources and assumptions listed in this report.

What the budget means per square foot.

Period Comparison
1981
Hard $43.6
Soft $3.8
Finance $4.4
Govt fees $1.6
Total $53.5
2000
Hard $88.5
Soft $7.7
Finance $4.3
Govt fees $2.7
Total $103.2
2020
Hard $141.8
Soft $12.3
Finance $5.7
Govt fees $40.7
Total $200.4
2025
Hard $274.9
Soft $23.8
Finance $14.3
Govt fees $73.1
Total $386.1
H1 2026
Hard $275.4
Soft $23.8
Finance $10.2
Govt fees $73.3
Total $382.7

Table 2. Nominal dollars per above-grade square foot for the fixed 2,000 sq. ft. house. The denominator excludes its unfinished basement. These are project costs, not sale prices. [18]

This is why a construction quote of around $238 per square foot and a project budget of around $383 can both be reasonable descriptions of the same example. The first describes the base building work. The second includes the other items required by our stated scope. Before comparing two quotes, ask what each includes and which area each uses.

Inflation does not explain the whole increase.

Period Comparison
1981
Nominal total $107,000
In H1 2026 purchasing power $362,000
2000
Nominal total $206,000
In H1 2026 purchasing power $362,000
2020
Nominal total $401,000
In H1 2026 purchasing power $490,000
2025
Nominal total $772,000
In H1 2026 purchasing power $788,000
H1 2026
Nominal total $765,000
In H1 2026 purchasing power $765,000

Table 3. Original model totals adjusted by Canada all-items CPI. Rounded to the nearest $1,000. CPI measures consumer purchasing power, not household income or construction productivity. [3] [4]

In this model, the 1981 and 2000 budgets are each about $362,000 in H1 2026 purchasing power. The H1 2026 budget is more than twice that amount. That is a useful signal, but the early backcasts and their embedded-tax treatment are too uncertain to support a precise claim about a 45-year increase in the cost of an identical completed house.

A range is more useful than a precise looking point estimate.

Keeping the other assumptions unchanged, the low and high ends of the Altus range produce H1 2026 project budgets of about $667,000–$864,000, or $334–$432 per square foot. Those are model sensitivities, not confidence limits. For 1981 and 2000, moving the backcast building estimate up or down by 20% changes the total to about $86,000–$128,000 and $166,000–$247,000, respectively. These deliberately chosen tests show how much the early estimates depend on the construction assumption.

How much of the difference comes from larger houses.

The house itself has changed. Statistics Canada’s 2018 property data show that newer detached-home cohorts in the Toronto CMA were generally larger. The same pattern appears across Ontario, although the provincial homes were smaller than the Toronto CMA homes in the selected cohorts. [19]

Construction cohort Comparison
1971–1980
Toronto CMA median 1,720 sq. ft.
Ontario median 1,330 sq. ft.
1981–1990
Toronto CMA median 2,240 sq. ft.
Ontario median 1,850 sq. ft.
1991–2000
Toronto CMA median 2,340 sq. ft.
Ontario median 1,830 sq. ft.
2006–2010
Toronto CMA median 2,580 sq. ft.
Ontario median 2,170 sq. ft.
2016–2017
Toronto CMA median 2,890 sq. ft.
Ontario median 2,380 sq. ft.

Table 4. Above-grade area of single-detached property stock measured in 2018, by original construction period. These are surviving-stock medians, not annual average sizes at the time of construction. [19]

For a second comparison, apply 2,240 square feet to the 1981 cost assumptions and 2,340 to 2000. Use 2,890 for the later dates as an explicit larger-house scenario. The last figure comes from the 2016–2017 cohort; it is not a measured average for homes built in 2020, 2025 or 2026.

Period / area Comparison
1981 / 2,240
Hard $42.7
Soft $3.7
Finance $4.3
Govt fees $1.5
Total / sq. ft. $52.2
2000 / 2,340
Hard $86.0
Soft $7.4
Finance $4.1
Govt fees $2.4
Total / sq. ft. $99.9
2020 / 2,890
Hard $133.0
Soft $11.5
Finance $4.9
Govt fees $28.5
Total / sq. ft. $177.9
2025 / 2,890
Hard $258.0
Soft $22.3
Finance $12.4
Govt fees $51.2
Total / sq. ft. $343.9
H1 2026 / 2,890
Hard $258.4
Soft $22.4
Finance $9.5
Govt fees $51.3
Total / sq. ft. $341.5

Table 5. Proposed larger-house scenarios: all amounts per above-grade sq. ft. The corresponding total budgets are $117,000, $234,000, $514,000, $994,000 and $987,000, rounded. These use the same Toronto fee case, not fees representative of every municipality in the CMA. [19]

The scaling rule holds 20% of building cost fixed and lets 80% rise with floor area. It is an assumption, not a measured economy of scale. Site work, contingency and soft allowances follow building cost; City and education DCs remain per dwelling. The workbook also tests a fully proportional building-cost alternative.

At H1 2026 prices, moving from 2,000 to 2,890 square feet adds about $222,000, lifting the total to $987,000. Yet the unit cost falls from $383 to $342 because the fixed costs are spread over more space. If all building cost grows with area, the larger-house total is about $1.042 million, or $361 per square foot. Either way, the lower cost per square foot does not mean the larger home is cheaper to build.

Two published Toronto examples.

A modest bungalow costed at August 2000 prices.

CMHC’s Residential Housing Study provides a useful historical check. Hanscomb costed the same 100-square-metre bungalow in several markets, including Toronto, at August 31, 2000 prices. The Toronto version had an unfinished basement, excluded from its 1,076-square-foot denominator. This was a professionally costed plan, not a recorded sale or an invoice from a completed house. [20]

Toronto costed plan August 2000 amount
Building work $73,183
Site items including steps and deck $5,044
General requirements at 9% $7,040
Total $85,267
Cost per above-grade sq. ft. $79.22

Table 6. CMHC/Hanscomb, report dated February 2003, Volume 1 Exhibit B. The total excludes contingency; permits are already within general requirements. Land and broader development costs are not included. Tax and profit treatment are not fully specified for the Canadian rate. [20] [28] [29]

That roughly $79 per square foot is a useful sense-check beside our 2000 model’s base building allowance of roughly $77. It does not validate the whole budget: the bungalow is smaller, its form differs, and its inclusions are not identical. It does show why historical examples must be read with their specification and area definition attached.

The same budget can produce two very different unit costs.

A second CMHC-commissioned study, costed by BTY in July 2017, modelled five detached houses built concurrently on serviced suburban lots. The Toronto example totalled $942,800 per house excluding land. It included $683,100 in construction before a separate construction-tax allowance, $41,000 for that tax allowance, $112,200 in non-financing soft costs, $92,000 in municipal/connection fees and $14,500 in financing. These figures regroup the source’s cost lines; its assumptions and scope differ from our benchmark. The tax allowance is not a statutory tax rate. [21]

The report described 2,300 square feet above grade but used 3,855 square feet of gross floor area for costing. Dividing the same $942,800 by those two areas gives about $410 and $245 per square foot. Nothing about the budget changed. Only the denominator changed. The study’s construction specification, contingency and soft-cost scope also differ from our benchmark, so it should not be read as proof of a price increase or decline between 2017 and 2026. [21]

The lesson for a client reviewing estimates is straightforward: ask for the full dollar budget, the area calculation and the exclusions before deciding that one builder or one generation is cheaper.

Which inputs have changed the most.

Lumber attracts attention because its price can move abruptly. Over the full 1981–H1 2026 comparison, however, concrete blocks and bricks rose more than the other selected material series. Their producer-price index increased 419%, or about 53% after consumer inflation. Softwood rose 232% in dollars but was about 2% lower after the same inflation adjustment. [1] [3] [4]

Inflation-adjusted changes in selected material and wage indexes from 1981 to H1 2026. Concrete blocks and bricks lead at 53.5%; veneer and plywood fall 23.9%.

Figure 1. Selected input changes after Canada CPI, 1981 annual average to H1 2026. Materials are national factory-gate prices. The Toronto wage series includes selected supplements and is an industrial-sector union proxy. [1] [2] [3] [4]

The leading material also changes with the starting point. Gypsum leads these selected series from 1981 to 2000; softwood leads from 2000 to 2020; metal windows and doors narrowly lead concrete masonry after 2020. A historical winner is not automatically the item that will drive the next project over budget.

These indexes tell us about prices at a particular stage of production. They do not tell us what a Toronto builder paid for delivered and installed work. Concrete blocks and bricks are concrete masonry products, not clay brick. The metal-window series is not a proxy for every vinyl or wood window. The wage series covers union agreements in the industrial sector, not the exact subcontract mix used to build our house. [5] [6]

Budget size matters too. In the workbook’s separate six-input example, labour begins at $100,000 of a $200,000 basket in 2020. Its 19.6% index increase adds about $19,630 by H1 2026, more dollars than any other selected line even though concrete prices grow faster. That result follows from the assumed weights; it is not evidence that labour caused 52% of an actual house’s cost increase.

Why cheaper lumber does not restore the old budget.

For recent years, Toronto’s detached-house Building Construction Price Index gives a broader view than the selected material basket. It measures contractor pricing for a representative building, including installation, equipment, overhead and profit. From the 2020 annual average to H1 2026 it rose 94.2%, compared with 22.3% for Canada CPI. [3] [4] [7] [8]

Toronto detached construction price index and Canada CPI rebased to 2020 equal 100. Construction reaches 194.2 in H1 2026 while CPI reaches 122.3.

Figure 2. Annual averages through 2025; January–June mean for 2026. The contractor measure and CPI answer different questions; neither is a home-price index. [3] [4] [7]

Over that same interval, installed wood/plastics/composites pricing rose 191.9%, while the national softwood producer index ended 2.0% below its 2020 annual average. Those observations are not contradictory. They describe different baskets, locations and stages of the supply chain. They do not provide enough information to assign the gap precisely among labour hours, other materials, margins, distribution and productivity. [1] [7]

The 2020 starting point also matters. H1 2026 softwood remained 35.8% above its 2019 annual average. Statistics Canada’s supply-chain study traces the pandemic surge to strong housing and renovation demand alongside mill shutdowns and timber constraints. It also finds uneven pass-through between supply-chain stages. A fall at the mill therefore need not deliver the same percentage saving to the customer buying an installed framing package. [1] [9]

The recent news is less severe than the cumulative increase suggests. The detached index averaged 105.825 in 2025 and 106 in H1 2026: little movement on top of a much higher cost base. That supports a distinction between costs stabilising and costs returning to their old level.

Government charges taxes and the cost of time.

Period Comparison
1981
City DC or levy $2,500 assumed
Education DC Not applicable
Mean prime 19.38%
2000
City DC or levy $3,912
Education DC $0
Mean prime 7.24%
July 2020 fee case
City DC or levy $76,830
Education DC $2,093
Mean prime 2.77%
July 2025 fee case
City DC or levy $137,846
Education DC $3,593
Mean prime 4.91%
H1 2026
City DC or levy $137,846
Education DC $3,893
Mean prime 4.45%

Table 7. Dated Toronto fees and annual/H1 means of weekly Bank of Canada prime observations. A separate permit/admin allowance equals 1% of base building cost. The 1981 levy is not an observed tariff and must not be used to rank historical fee growth. [10] [11] [12] [22] [23] [24]

The observed City DC rises from $3,912 for the selected former-Scarborough case in 2000 to $137,846 in the H1 2026 case. This is a charge for a specific jurisdiction and dwelling type, not a complete measure of everything governments required of development in either year. Earlier subdivision and servicing obligations are especially important when comparing generations.

Payment timing also changes the budget. Toronto moved ordinary non-rental residential DC payment to before occupancy from November 3, 2025. Our 2025 example assumes a permit before that change, while H1 2026 pays the City DC at occupancy. The model’s financing cost consequently falls from about $28,600 to $20,500, also helped by lower average prime. About $6,700 of the H1 saving comes from the DC timing alone. It is not a decline in the underlying hard cost. [17] [24]

Toronto’s conditional July 2026 programme would reduce the qualifying single/semi DC to $55,138. Applying that later policy scenario to the H1 cost base reduces our total from about $765,000 to $682,000, including the smaller assumed lender fee. The executed provincial agreement and project eligibility were not verified, so this is a separate conditional scenario, not the H1 rate or a universal current entitlement. [13] [14]

Why the model does not add 13 percent to every line.

For the registered developer in this example, eligible input GST/HST is paid and then recovered through input tax credits. Its assumed additional permanent cost is therefore zero. That does not mean construction is untaxed: historical nonrecoverable material taxes were embedded in prices, and a delay in recovering tax can require financing. Our model does not isolate those historical taxes or finance the recovery delay. [25] [26]

An owner commissioning a house may face a different cash bill and rebate position. As a simple H1 illustration, 13% on the $476,800 base building work alone is about $62,000 before any rebate. That is not the tax on the full project. A household comparison requires taxable-service details, land value, eligibility and construction dates; rebates should not be assumed from a land-excluded budget. [25] [26] [27]

What this means for a property decision.

For a builder assessing a lot, work backwards from a selling price supported by comparable sales and current demand. Deduct the complete construction and project budget, selling costs and the return required for taking the risk. What remains is the amount available for land. If construction costs rise while achievable prices stay flat, the first consequence may be less support for land value or a decision not to build.

For an owner commissioning a home, compare builders on a shared specification. Request the same above-grade area, basement scope, site assumptions, tax treatment and contingency. A lower headline rate can be less attractive once excluded work is added. Keep a separate allowance for unusual ground conditions and changes to the design.

For lenders, the budget matters alongside the as-completed value. A high replacement cost does not establish that the finished property will sell for that amount. Review the cost-to-complete, cash available for charges, draw schedule, interest reserve and evidence supporting the exit price. A project can have a sound structure and still lack enough margin to cover a delay.

What could change this assessment.

The strongest counterargument is that a benchmark can miss genuine savings. A simpler plan, repeat construction, a serviced site, procurement improvements or a competitive tender may beat a broad cost guide. Larger floor area can lower the unit rate, while smaller homes can lower the total cheque. The guide range and the size sensitivities show how much reasonable changes to assumptions matter.

There is also a quality difference across generations. Modern safety, comfort and performance are not identical to those of a 1981 home. This paper cannot price that change separately. It would be misleading to attribute the unexplained increase to regulation alone: Ontario’s July 2024 code bulletin, for example, states that the 2024 edition made no technical change to the SB-10/SB-12 energy requirements, even while other provisions changed. [16]

Fresh tenders for the defined house, a historical bill of quantities, confirmed fee eligibility or a different construction schedule would justify revising the estimates. The most useful indicators to follow are the Toronto detached BCPI, actual trade bids, municipal fee/payment rules, financing terms and achievable selling prices. No series here can quantify a local sale-price or land-value response by itself.

Conclusion.

An ordinary house is more expensive to deliver for several reasons, and their importance changes over time. The recent increase in our same-size example is driven mainly by hard construction costs, followed by government fees. Building more space adds another substantial cost, even when the dollars per square foot fall. The practical answer is to compare the same scope first, then show clearly what changes when the house, the financing or the policy changes.

How the estimates were built.

The accompanying workbook contains the source observations, editable assumptions, complete formulas and sensitivity cases. Published facts, index calculations and analyst allowances are kept in separate rows. Displayed dollar amounts are rounded; calculations retain precision.

  • Modern base building cost C = 2,000 × $237.50 × Toronto detached BCPI(period) / 105.6. The guide is dated January 31, 2025; Q1 2025 is the nearest quarterly index match. Period indexes are 54.575 for 2020, 105.825 for 2025 and 106 for H1 2026. The guide midpoint is not a market mean.
  • For 1981 and 2000, C = C(2020) × selected-input basket(period) / basket(2020). The hypothetical 2020 weights are labour 50%, softwood 20%, ready-mix 12.5%, concrete masonry 5%, plywood 7.5% and gypsum 5%. This applies a partial basket’s movement to the whole building as a scenario assumption; it does not measure omitted trades, productivity or changing margins.
  • Hard costs H = C × 1.05 × 1.10, including the 5% site allowance and 10% construction contingency. Soft costs S = 10% × C, covering assumed professional work, insurance and project administration. Permits are kept out of these allowances and shown separately at 1% × C.
  • Government fees G = selected City DC/levy + education DC + 1% × C. Use July 2020 and July 2025 tariff snapshots, not annual-average fees. The 2000 case uses the former-Scarborough tariff after the transition cutoff. No 1981 comparable tariff was recovered: $2,500 is an allowance, with a $0–$5,000 test.
  • Finance = 0.75 × [0.5 × (H + S) + t × City DC + education DC + permit allowance] × (mean prime + 0.02) × 12/12 + 0.01 × 0.75 × (H + S + G). Here t = 1 for the assumed upfront City DC through the 2025 case and 0 for H1 2026 occupancy payment. Other fees are assumed upfront. The 75% financing share, 2-point spread, 12-month duration, uniform draws and 1% lender fee are assumptions, not observed loan offers.
  • Total = H + S + G + finance. Interest is not capitalised into its own calculation; the facility excludes finance to avoid circularity. Land carry, approval delays before construction and GST/HST recovery timing are excluded.
  • For a house of area A, C(A) = C(2,000) × [0.20 + 0.80 × A / 2,000]. The alternative replaces this with C(2,000) × A / 2,000. Cost per square foot = total / above-grade area. Real H1 2026 dollars = nominal total × CPI(H1 2026) / CPI(period).

Important limits: the 1981/2000 full budgets are lower-confidence backcasts; their tax basis cannot be fully harmonised. National material prices and industrial-sector Toronto union wages do not exactly match residential delivered costs. Historical stock-size cohorts are not annual new-build size surveys. The 2026 Altus numerical guide was gated and was not used; the available 2025 guide was read from a public mirror.

Draft 2 replaces the earlier paper’s arbitrary $350,000 construction allowance for 2020 with the sourced Altus 2025 range and a documented index adjustment. The resulting level change is a change in modelling basis, not evidence that market construction costs fell.

Sources.

  1. Statistics Canada — Industrial product price index, by product, monthly, Table 18-10-0266-01 Released September 17, 2026. Canada; selected product rows; January 2020=100. Annual means 1981–2025 and January–June 2026 calculated from monthly CSV. Latest available month August 2026; common comparison deliberately ends June.
  2. Statistics Canada — Construction union wage rate index, monthly, Table 18-10-0140-01 Released July 17, 2026. Toronto composite trade index, basic rates and rates including selected supplements; 2015=100; January 1971–June 2026 available.
  3. Statistics Canada — Consumer Price Index, annual average, Table 18-10-0005-01 Released January 19, 2026. All-items Canada, Ontario and Toronto; 2002=100; annual observations through 2025.
  4. Statistics Canada — Consumer Price Index, monthly, Table 18-10-0004-01 Released September 14, 2026. All-items, not seasonally adjusted. January–June 2026 mean used for the report; Canada 167.483333, Toronto 169.733333.
  5. Statistics Canada — Technical Guide for the Industrial Product Price Index October 20, 2025; sections 3.1, 3.5, 3.6 and 4. Factory-gate scope, exclusions, quality adjustment, basket linking and revisions.
  6. Statistics Canada — Construction Union Wage Rate Index, survey 2307 Detailed information for January–June 2026. Industrial-sector journeyman agreements, selected supplements, trade weights and historical linking. A wage-rate proxy, not residential subcontract quotations.
  7. Statistics Canada — Building construction price indexes, by type of building and division, Table 18-10-0289-01 Released July 24, 2026. Toronto, Single-detached house [621112], composite and divisions; 2023=100. Detached observations begin Q1 2017. Composite vector v1617912708.
  8. Statistics Canada — Technical Guide for the Building Construction Price Index, 2023 June 6, 2025; sections 1–2, 4.1–4.3, 5.4 and Appendix A.1. Contractor-price scope, representative projects, weighting and linking.
  9. Statistics Canada — Prices through the supply chain: Softwood lumber Robert Meyer-Robinson, September 2, 2022. Historical pandemic demand/supply evidence and price transmission. Its 65% wood contribution applies to the 11-CMA detached composite, Q1 2020–Q1 2022, not this report’s Toronto period.
  10. City of Toronto — By-law 476-1999 Schedule A, PDF p.12; sections 27, 31 and 33. Fully phased city-wide single/semi amount $3,912 from September 1, 2001; indexing starts September 2002. Earlier transitional rates differed by former municipality.
  11. City of Toronto — Development Charges, November 1, 2019 PDF p.1. Single/semi total $76,830.
  12. City of Toronto — Development Charge Rates effective June 26, 2025 PDF p.1, non-rental residential single/semi $137,846. Still linked as base schedule by current City rates page at October 7, 2026 cutoff.
  13. City of Toronto — By-law 1261-2026 Enacted July 30, 2026; PDF pp.3–5, Schedule D and Appendix D.1. Conditional single/semi reduction to $55,138; agreement and project milestones apply. Original PDF downloaded and read; one later web-render attempt failed.
  14. City of Toronto — Development Charges programme status Accessed October 7, 2026. City states reduction programme is subject to a provincial Transfer Payment Agreement. Execution was not verified; do not treat the reduced rate as universally effective.
  15. Housing, Infrastructure and Communities Canada — Canada and Ontario Making Homes More Affordable in Barrie September 28, 2026. Up to about $129 million linked to a residential DC reduction commitment. Funding is conditional on agreements, review and approvals; no independent buyer-price effect established.
  16. Ontario Ministry of Municipal Affairs and Housing — 2024 Building Code: Key Changes Technical Bulletin July 2024, ministry-authored bulletin hosted by CodeNews; p.85 soil-gas measures; p.107 states no technical change to SB-10/SB-12 energy requirements in the 2024 edition. Explanatory document, not legislation.
  17. City of Toronto — Non-rental Residential Development Charges Accessed October 7, 2026. Effective November 3, 2025, payment for non-rental residential DCs shifted to payment in full before occupancy; individual agreements may differ.
  18. Altus Group — 2025 Canadian Cost Guide Altus-authored guide, released March 27, 2025; costs as of January 31, 2025. PDF p.5 GTA single-family unfinished-basement $200–$275/sq. ft.; pp.10–12 scope/area exclusions. Read original PDF via public mirror; web-render endpoint failed. 2026 gated numerical guide not used.
  19. Statistics Canada — Residential property characteristics by construction period, Table 46-10-0028-01 2018 reference year; released May 3, 2019. Single-detached median above-grade area, Ontario and Toronto CMA, selected construction cohorts. Full CSV and metadata retained; areas describe stock observed in 2018, not annual new-house averages.
  20. CMHC and Hanscomb — Residential Housing Study, Volume 1 Report February 2003; cost date August 31, 2000. Exhibit B, physical PDF p.37: Toronto 100 m² bungalow with basement; cost-date/method pp.11–13. Vol.3 p.A31 shows general requirements including permits; Vol.4 p.B25 specifies steps and deck (same publication series, suffixes -3-eng.pdf and -4-eng.pdf).
  21. CMHC commissioned study — Cost of Delivering Housing in Canada RDH/BTY, submitted November 24, 2017; BTY costing July 20, 2017. Appendix A Table 5, physical PDF p.64 (BTY p.11); detailed detached model pp.74–75. Class C estimates, ±15–20% source accuracy. Five houses built concurrently; Toronto $942,800 excluding land; 2,300 sq. ft. above grade versus 3,855 sq. ft. costing GFA.
  22. City of Toronto — Education Development Charges Accessed October 8, 2026. TCDSB residential $2,093 May 1, 2020–April 30, 2021; $3,593 December 3, 2024–December 2, 2025; $3,893 December 3, 2025–December 2, 2026. Payable with applicable first above-ground permit.
  23. TCDSB — Education Development Charges Background Study August 14, 2023. Section 1.2, printed p.2 / physical PDF p.17: TCDSB EDCs imposed since March 27, 2001. Supports zero TCDSB EDC in 2000, not zero for all possible historic school-site obligations.
  24. Bank of Canada — Posted prime rate, weekly series V80691311 Downloaded October 8, 2026. Simple arithmetic mean of weekly Wednesday observations: 52 in 1981, 52 in 2000, 53 in 2020, 53 in 2025 and 25 in H1 2026. Prime benchmark only; hypothetical construction terms added separately.
  25. Canada Revenue Agency — RC4052 GST/HST Information for the Home Construction Industry Accessed October 8, 2026. Sections on provincial sales tax, claiming input tax credits and construction services. Eligible commercial input GST/HST recoverable; historical nonrecoverable PST may be embedded in contractor prices.
  26. Canada Revenue Agency — GST/HST Statistics Tables, jurisdiction rate history Published August 12, 2026; historical rate table. GST began January 1991 at 7%; Ontario HST 13% from July 2010. Rates alone do not establish a permanent cost or rebate entitlement.
  27. Canada Revenue Agency — RC4028 GST/HST New Housing Rebate 2026 guide accessed October 8, 2026. Owner-built eligibility, land-inclusive completed value and timing conditions; distinguishes ordinary, first-time-buyer and enhanced Ontario rebate provisions. No household rebate is quantified in this report.
  28. CMHC and Hanscomb — Residential Housing Study, Volume 3 February 2003; August 31, 2000 costs. Physical PDF p.41, printed A31: Toronto general requirements include permits, cleaning, temporary power, fencing and site accommodation.
  29. CMHC and Hanscomb — Residential Housing Study, Volume 4 February 2003; August 31, 2000 costs. Physical PDF p.35, printed B25: Toronto site items include precast steps and a 15 m² cedar deck; these do not represent off-site servicing.
Peter Jordon

Peter Jordon, CPA, CA, AACI, P.App. | Broker

Jordon Real Estate Advisory Services

Put these costs in the context of your property.

If you are weighing a purchase, a sale or a development decision, let’s put the costs and the local market evidence together.

Research draft for review. General information and illustrative analysis, not a property-specific appraisal, cost certification or financing commitment. Formal appraisal services are separate engagements.